Successfully completes preventive and corrective maintenance of the Tuy III System

Tuy III System Maintenance
Courtesy

Published at: 13/10/2026 02:03 PM

The scheduled shutdown for preventive and corrective maintenance in the Tuy III System ended successfully in the early hours of the morning of this Tuesday, tasks that will benefit, with the drinking water supply service, the population of Caracas, Miranda and La Guaira.

This was reported by the president of Hidroven, Claudio Bastiani, who explained that since October 11, specialized personnel were able to attend to 41 actions planned in the five fronts of work that were carried out throughout the system.

“We verified the structure of the line. In addition, preventive maintenance work was carried out on the valves, suction cups and equipment, and on the Caujarito water treatment plant,” he added.

Bastiani indicated that Hidroven personnel are currently in the start-up phase of pumping vital liquid through the intervened system, which complies with the corresponding safety protocols.

He expressed his pride to “see the effort, dedication and mystique of our workers during the nights.” It has been a day of uninterrupted work, in which the technical water team demonstrated once again what it is made of,” he said.

The Secretary of Water of Miranda State, Karol Merchan, was present during the night days of maintenance work on the Tuy III System, who indicated that with these tasks, more than 330 additional liters per second will be added to Caracas, Miranda and La Guaira.

Mazo News Team/VTV