Governor Luis Caldera supervised the electrical connection of Turkish barges to reinforce the national system
Luis Caldera Instagram
Published at: 24/11/2026 06:01 PM
The infrastructure installation to incorporate two floating power generation units from the Turkish company Karpowership to the Ramón Laguna Thermoelectric Plant, in the Los Haticos sector of Maracaibo, is progressing with the construction of towers and transmission lines, said this Tuesday, November 24, the governor of the state of Zulia, Luis Caldera.
The regional president explained that the work will make it possible to establish a connection with the vessels once they arrive in the country.
“Right now, the lines are being built at our Ramón Laguna plant, with transmission towers and distribution lines, which will allow, after the barges arrive and after the announcements made by our minister Rolando Alcalá, the details of the installation of these barges, to boost electricity generation in the Zulian region,” said the governor, quoted in a press release.
The initiative is part of the international agreement announced by the President of the Republic, Delcy Rodríguez, to contribute to the stabilization of the National Electric System (SEN) in western Venezuela.
The plan envisages adding up to 500 additional megawatts before the end of 2026.
In parallel, crews from the National Electric Corporation (CORPOELEC) began laying high-voltage lines in Maracaibo this Tuesday, as part of the works necessary to connect floating units to the national electrical system.
The project is being developed within the framework of the agreement signed on November 4th between CORPOELEC and the Turkish company Karpowership.