CORPOELEC restores power distribution in western Anzoátegui after completing works

The work was carried out to resolve a fault in the high-voltage power supply
Photo: CORPOELEC press

Published at: 19/11/2026 01:19 PM

The National Electric Corporation (CORPOELEC) completed the energization maneuvers of the 115KV José-Isleta-Clarines line to restore electricity supply in the Peñalver, Píritu, Bruzual, Carvajal and Capistrano municipalities in the state of Anzoátegui.

The work was carried out to solve a fault in the high voltage line generated by the detachment of the guard cable in a section located between spans 23, 24 and 25, which supplies the main substations that supply these locations on the western axis of Anzoátegui and that border the states of Miranda and Guárico.

The limited access of vehicles to the site, because it is a mountainous area, increased the complexity of these works, which were carried out on structures greater than 20 meters in height, during a day carried out by 30 workers that lasted more than 24 hours continuously and that did not end until the fault was corrected.

It should be noted that during the maneuvers, a second fault was detected and was solved with the replacement of the hardware in phase A and C.

In this way, the National Electric Corporation confirms its commitment to the Venezuelan people to continue carrying out tasks to guarantee good electricity service.