CORPOELEC performs corrective maintenance on the Aragüita circuit
Photo: CORPOELEC press
Published at: 02/11/2026 11:21 AM
Crews from the National Electric Corporation (CORPOELEC) carried out corrective maintenance on the Araguita circuit, Acevedo municipality in Miranda state.
The work included the replacement of system components, including crosspieces, plates, clamps and insulators.
Similarly, in the Los Silos sector, they installed a new 50 kVA transformer and replaced a medium-voltage pole that presented a hazardous condition.
The corrective actions also included clearing vegetation close to electrical lines and structures, to facilitate energy distribution in communities in the Barloventeño region.
These maneuvers are included in the Plan for the Adaptation and Maintenance of Substations and Electrical Circuits, which CORPOELEC is carrying out throughout the state of Miranda.