78% of progress have been made to recover roads on the La Yaguara-El Junquito highway

The works seek to guarantee mobility and road safety in the Capital
Photo: Courtesy

Published at: 03/11/2026 01:57 PM

The construction of the system of micropiles connected with a mooring beam at kilometer 3+300 of the La Yaguara-El Junquito highway is more than 78% complete, as part of the work carried out in the El Junquito parish of the Libertador municipality to strengthen traffic and road safety in the capital, the Ministry of Transport reported in a publication on its Telegram channel.

At the same time, technical crews recorded 58% progress in addressing the edge fault located on the progressive 3+580. At this point, specialized tasks are carried out that include the removal of piles, the installation of reinforcing steel and the compaction of the soil.

“We mobilize for the people! To ensure mobility and road safety in the Capital, our technical teams are still deployed in the El Junquito parish of the Libertador municipality,” the Transportation portfolio highlighted on its Telegram channel.

https://t.me/mintransporte_ve/2333?single

Mazo News Team